Maximizing the expected net present value of a project with phase-type distributed activity durations: An efficient globally optimal solution procedure

Archive ouverte : Article de revue

Creemers, Stefan

Edité par HAL CCSD ; Elsevier

International audience. We study projects with activities that have stochastic durations that are modeled using phase-type distributions. Intermediate cash flows are incurred during the execution of the project. Upon completion of all project activities a payoff is obtained. Because activity durations are stochastic, activity starting times cannot be defined at the start of the project. Instead, we have to rely on a policy to schedule activities during the execution of the project. The optimal policy schedules activities such that the expected net present value of the project is maximized. We determine the optimal policy using a new continuous-time Markov chain and a backward stochastic dynamic program. Although the new continuous-time Markov chain allows to drastically reduce memory requirements (when compared to existing methods), it also allows activities to be preempted; an assumption that is not always desirable. We prove, however, that it is globally optimal not to preempt activities if cash flows are incurred at the start of an activity. Moreover, this proof holds regardless of the duration distribution of the activities. A computational experiment shows that we significantly outperform current state-of-the-art procedures. On average, we improve computational efficiency by a factor of 600, and reduce memory requirements by a factor of 321.

Consulter en ligne

Suggestions

Du même auteur

Collaborative Shipping : Logistics in the Sharing Economy

Archive ouverte: Article de revue

Beliën, Jeroen | 2017-04

International audience

A column generation approach for solving the examination-timetabling proble...

Archive ouverte: Article de revue

Woumans, Gert | 2016-08

International audience

Evaluation of appointment scheduling rules: A multi-performance measurement...

Archive ouverte: Article de revue

Creemers, Stefan | 2021-04

International audience. Appointment scheduling rules are used to determine when a customer is to receive service during a service session. In general, appointment scheduling rules do not consider the sequencing of i...

Du même sujet

Élaborer un projet d'établissement ou de service en action sociale et médic...

Livre | Loubat, Jean-René (1953-....). Auteur | 2012 - 3e édition

Conduire un projet dans les services : 75 fiches à l'usage des responsables...

Livre | Chambon, Martine. Auteur | 2008 - 5e édition

Project planning with alternative technologies in uncertain environments

Archive ouverte: Article de revue

Creemers, Stefan | 2015-04

International audience. We investigate project scheduling with stochastic activity durations to maximize the expected net present value. Individual activities also carry a risk of failure, which can cause the overal...

The preemptive stochastic resource-constrained project scheduling problem

Archive ouverte: Article de revue

Creemers, Stefan | 2019-08-16

International audience. Preemption (or the splitting of activities) is a common practice in many project environments, and has been a standard feature of commercial project management software packages for years. De...

Dynamic order acceptance and capacity planning in a stochastic multi-projec...

Archive ouverte: Article de revue

Melchiors, Philipp | 2017-10-31

International audience. We study the integration of order acceptance and capacity planning in multi-project environments with dynamically arriving projects. We model this planning problem as a continuous-time Markov...

« Conciliation vie privée vie professionnelle » : plusieurs termes pour une...

Archive ouverte: Article de revue

Verstaevel, N. | 2020-12-31

Chargement des enrichissements...